|
Contract Law Page |
| CASES ON DISCHARGE OF CONTRACT |
|
1. PERFORMANCE THE GENERAL RULE Re Moore and Landauer [1921] 2 KB 519 There was an agreement for the sale of 3,000 tins of canned fruit packed in
cases of 30 tins. When delivered it was discovered that half the cases contained
only 24 tins although the total number of tins was still 3,000. The market value
was not affected. The Court of Appeal held that notwithstanding that there was
no loss to the buyer, he could reject the whole consignment because of the
breach of s13 of the Sale of Goods Act (goods must correspond with the
description).
Cutter v Powell (1795) 6 Term Rep 320 A seaman who was to be paid his wages after the end of a voyage died just a
few days away from port. His widow was not able to recover any of his wages
because he had not completed performance of his contractual obligation. However,
this situation is now provided for by the Merchant Shipping Act 1970. MODIFICATION OF THE GENERAL RULE Sumpter v Hedges [1898] 1 QB 673 The plaintiff agreed to erect upon the defendant's land two house and stables
for £565. He did part of the work to the value of about £333 and then
abandoned the contract. The defendant completed the buildings. The Court held
that the plaintiff could not recover the value of the work done, as he had
abandoned the contract. Roberts v Havelock (1832) 3 B. & Ad. 404 A shipwright agreed to repair a ship. The contract did not expressly state
when payment was to be made. He chose not to go on with the work. It was held
that the shipwright was not bound to complete the repairs before claiming some
payment. Note: GH Treitel, The Law of Contract, states (at p702): In such cases the
question whether a particular obligation is entire or severable is one of
construction; and where a party agrees to do work under a contract, the courts
are reluctant to construe the contract so as to require complete performance
before any payment becomes due. "Contracts may be so made; but they require
plain words to shew that such a bargain was really intended": Button v
Thompson (1869) LR 4 CP. Christy v Row (1808) 1 Taunt 300 A ship freighted to Hamburg was prevented 'by restraint of princes' from
arriving. Consignees accepted the cargo at another port to which they had
directed it to be delivered. The consignees were held liable upon an implied
contract to pay freight pro rata itineris (ie, for freight at the contract rate
for the proportion of the voyage originally undertaken which was actually
accomplished). A contract was implied from their directions re alternative port
of delivery. Planche v Colburn (1831) 8 Bing 14 The plaintiff was to write a book on 'Costume and Ancient Armour' for a series, and was to receive £100 on completion of the book. After he had done the necessary research but before the book had been written, the publishers abandoned the series. He claimed alternatively on the original contract and on a quantum meruit. The court held that: (a) the original contract had been discharged by the
defendants' breach; (b) no new contract had been substituted; and (c) the
plaintiff could obtain 50 guineas as reasonable remuneration on a quantum meruit.
This claim was independent of the original contract and was based on
quasi-contract. Dakin v Lee [1916] 1 KB 566 The defendants promised to build a house according to specification and
failed to carry out exactly all the specifications, for example, concrete not
four feet deep as specified, wrong joining of certain rolled steel joists and
concrete not properly mixed. The Court of Appeal held that the builders were
entitled to recover the contract price, less so much as ought to be allowed in
respect of the items found to be defective. Bolton v Mahadeva [1972] 2 All ER 1322 The plaintiff agreed with the defendant that he would install central heating
in the defendant's house for a lump sum of £560. When the work was completed,
the defendant complained that it was defective and refused to pay. The judge
found that the flue was defective so that it gave off fumes making the rooms
uncomfortable, and the system was inefficient in that the amount of heat varied
from one room to another. The cost of rectifying these defects was £174. The
Court of Appeal held that the plaintiff was not entitled to recover as there had
been no substantial performance. Startup v M'Donald (1843) 6 M&G 593 The plaintiffs agreed to sell 10 tons of oil to the defendant and to deliver
it to him 'within the last 14 days of March', payment to be in cash at the end
of that period. Delivery was tendered at 8.30pm on 31 March. The defendant
refused to accept or pay for the goods because of the late hour. The court held
that the tender was equivalent to performance and the plaintiffs were entitled
to recover damages for non-acceptance. Today note s29(5) SGA 1979: Demand or
tender of delivery may be treated as ineffectual unless made at a reasonable
hour; and what is a reasonable hour is a question of fact. 2. AGREEMENT No cases. 3. BREACH Vitol SA v Norelf Ltd [1996] 3 All ER 193 The repudiating party notified the other that they considered the contract at an end. However, no action was taken by the innocent party, either to act on the repudiation or to affirm the contract, on receipt of this information. The Court of Appeal stated that inactivity did not show the party's intentions one way or another and did not amount to acceptance of repudiation or serve as affirmation either. This decision was reversed by the House of Lords, who held that silence or inaction can amount to acceptance of a wrongful repudiation of a contract.
An employer told is employee (a travelling courier) before the time for
performance arrived that he would not require his services. The courier sued for
damages at once. The court held that he was entitled to do so. Avery v Bowden (1855) 5 E&B 714 A charterparty provided that a ship should proceed to Odessa and there take a
cargo from the charterer's agent. The ship arrived at Odessa and the master
demaned a cargo, but the agent could not provide one. The ship's master
continued to ask for one. A war broke out. The charterer sued. The court held,
inter alia, that if the agent's conduct amounted to an anticipatory repudiation
of the contract, the master had elected to keep the contract alive until it was
discharged by frustration on the outbreak of war. White & Carter v McGregor [1961] 3 All ER 1178 The plaintiff advertising contractors agreed with the defendant garage proprietor to display advertisements for his garage for three years. The defendant repudiated the agreement and cancelled on the same day. The plaintiffs refused to cancel and performed their obligations. They sued for the contract price. The House of Lords held, by a majority of 3:2 that they were entitled to the full contract price. See law report. Panchaud Freres SA v Establissments General Grain Co [1970] 1 Lloyd's Rep 53 Buyers of maize rejected it on a ground which was subsequently found to be
inadequate. Three years later, they discovered that the grain had not been
shipped within the period stipulated for in the contract. They, therefore,
sought to justify their rejection on this ground. The Court of Appeal held that
they were not entitled to do so. Lord Denning MR stated that the buyers were
estopped by their conduct from setting up late delivery as a ground for
rejection because they had led the sellers to believe they would not do so. Fercometal Sarl v Mediterranean Shipping Co [1988] 2 All ER 742 Charterers entered into a charterparty with the shipowners. The charterers cancelled the charterparty and engaged a different vessel. The owners did not accept the repudiation which was premature because it was given in advance of the cancellation date. When the vessel arrived the owners gave notice of readiness even though they were not in fact ready to load the charterers' cargo. The charterers rejected the notice and proceeded to load their cargo onto the other vessel. The shipowners brought an action for damages. The House of Lords held that where a party to a contract wrongfully repudiated his contractual obligations before he was required to perform those obligations, the innocent party could either affirm the contract, treating it as still in force, or treat it as being discharged. If he elected to affirm the contract he was not absolved from tendering his own performance under the contract. Thus if a repudiation by the anticipatory breach was followed by affirmation of the contract, the repudiating party could escape liability if the affirming party was subsequently in breach of his obligations under the contract. On the facts of the case the owners, having affirmed the contract when they
refused to accept the charterers premature repudiation, could avoid the
cancellation clause in the charterparty only by tendering the vessel ready to
load on time, which they had failed to do, or by establishing, which they could
not do, that their failure was due to their acting on a representation by the
charterers that they had given up their option to cancel. Federal Commerce & Navigation v Molena Alpha [1979] AC 757 Clause 9 of a charter provided that the charterers were to sign bills of lading stating the freight had been correctly paid. After a dispute arose concerning deductions made by the charterers, the shipowners withdrew this authority contrary to the terms of the charter. The master was instructed not to sign bills of lading with the indorsement 'freight pre paid' or which did not contain an indorsement giving the shipowners a lien over the cargo for freight. This meant that the charterers were put in an impossible position commercially. The charterers treated the owner's actions as a repudiation of the charter. The House of Lords held that although the term broken was not a condition,
the breach went to the root of the contract by depriving the charterers of
virtually the whole benefit of the contract because the issue of such bills was
essential to the charterers' trade. Therefore, the owner's conduct constituted a
wrongful repudiation of the contract. Woodar Investment v Wimpey Construction [1980] 1 WLR 277 Wimpey contracted to buy land for £850,000 and agreed to pay £150,000 on completion to a third party, Transworld Trade Ltd. The contract allowed the purchaser to rescind the contract if before completion a statutory authority 'shall have commenced' to acquire the property by compulsory purchase. At the date of the contract both parties knew that a draft compulsory purchase order had been made. Wimpey purported to terminate relying on this provision, and Woodar sought damages alleging that this amounted to a wrongful repudiation. Their damages claim included the loss suffered by the third party (as to which, see Privity of Contract). The House of Lords held, by a majority of 3:2, that in order to constitute a
renunciation of the contract there had to be an intention to abandon the
contract and instead of abandoning the contract Wimpey were relying on its terms
as justifying their right to terminate. 4. FRUSTRATION
Taylor v Caldwell (1863) 3 B&S 826 For facts, see below. Blackburn J stated: "The principle seems to us
to be that, in contracts in which the performance depends on the continued
existence of a given person or thing, a condition is implied that the
impossibility of performance arising from the perishing of the person or thing
shall excuse the performance." Davis Contractors v Fareham UDC [1956] AC 696 For facts, see below. Lords Reid and Radcliffe stated that the 'radical change in the obligation' test required the court to: 1. Construe the contractual terms in the light of the contract and
surrounding circumstances at the time of its creation. Taylor v Caldwell (1863) 3 B&S 826 Caldwell agreed to let a music hall to Taylor so that four concerts could be
held there. Before the date of the first concert, the hall was destroyed by
fire. Taylor claimed damages for Caldwell's failure to make the premises
available. The court held that the claim for breach of contract must fail since
it had become impossible to fulfil. The contractual obligation was dependent
upon the continued existence of a particular object. See above for the quote of
Blackburn J. Condor v The Baron Knights [1966] 1 WLR 87 A drummer engaged to play in a pop group was contractually bound to work on
seven nights a week when work was available. After an illness, Condor's doctor
advised that it was only safe to employ him on four nights a week, although
Condor himself was willing to work every night. It was necessary to engage
another drummer who could safely work on seven nights each week. The court held
that Condor's contract of employment had been frustrated in a commercial sense.
It was impracticable to engage a stand-in for the three nights a week when
Condor could not work, since this involved double rehearsals of the group's
music and comedy routines. Phillips v Alhambra Palace Co [1901] 1 QB 59 One partner in a firm of music hall proprietors died after a troupe of
performers had been engaged. The contract with the performers was held not to be
frustrated because the contract was not of a personal nature, and could be
enforced against the surviving partners. Graves v Cohen (1929) 46 TLR 121 The court held that the death of a racehorse owner frustrated the contract
with his employee, a jockey, because the contract created a relationship of
mutual confidence. FC Shepherd v Jeromm [1986] 3 All ER 589 The Court of Appeal held that a sentence of imprisonment imposed on an
employee was capable of frustrating the employee's contract of employment if the
sentence was such that it rendered the performance of the contract radically
different from that which the parties contemplated when they entered into the
contract. Krell v Henry [1903] 2 KB 740 Henry hired a room from Krell for two days, to be used as a position from
which to view the coronation procession of Edward VII, but the contract itself
made no reference to that intended use. The King's illness caused a postponement
of the procession. It was held that Henry was excused from paying the rent for
the room. The holding of the procession on the dates planned was regarded by
both parties as basic to enforcement of the contract. Herne Bay Steamboat Co v Hutton [1903] 2 KB 683 Herne Bay agreed to hire a steamboat to Hutton for a period of two days for
the purpose of taking passengers to Spithead to cruise round the fleet and see
the naval review on the occasion of Edward VII's coronation. The review was
cancelled, but the boat could have been used to cruise round the assembled
fleet. It was held that the contract was not frustrated. The holding of the
naval review was not the only event upon which the intended use of the boat was
dependent. The other object of the contract was to cruise round the fleet, and
this remained capable of fulfilment. Metropolitan Water Board v Dick Kerr [1918] AC 119 Kerr agreed to build a reservoir for the Water Board within six years. After
two years, Kerr were required by a wartime statute to cease work on the contract
and to sell their plant. The contract was held to be frustrated because the
interruption was of such a nature as to make the contract, if resumed, a
different contract. Denny, Mott & Dickinson v James Fraser [1944] AC 265 A contract for the sale and purchase of timber contained an option to
purchase a timber yard. By a wartime control order, trading under the agreement
became illegal. One party wanted to exercise the option. It was held that the
order had frustrated the contract so the option could not be exercised. Re Shipton, Anderson and Harrison Brothers [1915] 3 KB 676 A contract was concluded for the sale of wheat lying in a warehouse. The
Government requisitioned the wheat, in pursuance of wartime emergency
regulations for the control of food supplies, before it had been delivered, and
also before ownership in the goods had passed to the buyer under the terms of
the contract. It was held that the seller was excused from further performance
of the contract as it was now impossible to deliver the goods due to the
Government's lawful requisition. Jackson v Union Marine Insurance (1873) LR 10 CP 125 A ship was chartered in November 1871 to proceed with all possible despatch, danger and accidents of navigation excepted, from Liverpool to Newport where it was to load a cargo of iron rails for carriage to San Francisco. She sailed on 2 January, but the next day ran aground in Caernarvon Bay. She was refloated by 18 February and taken to Liverpool, where she underwent extensive repairs, which lasted till August. On 15 February, the charterers repudiated the contract. The court held that such time was so long as to put an end in a commercial
sense to the commercial speculation entered upon by the shipowner and the
charterers. The express exceptions were not intended to cover an accident
causing such extensive damage. The contract was to be considered frustrated. LIMITATIONS OF THE DOCTRINE Davis Contractors v Fareham UDC [1956] AC 696 The plaintiff agreed to build 78 houses in eight months at a fixed price. Due
to bad weather, and labour shortages, the work took 22 months and cost £17,000
more than anticipated. The builders said that the weather and labour shortages,
which were unforeseen, had frustrated the contract, and that they were entitled
to recover £17,000 by way of a quantum meruit. The House of Lords held that the
fact that unforeseen events made a contract more onerous than was anticipated
did not frustrate it.
T agreed to sell Sudanese groundnuts to NT, the nuts to be shipped from Port
Sudan to Hamburg, November/December 1956. As a result of the 'Suez crisis', the
Suez Canal was closed from 2 November 1956 until April 1957. T failed to
deliver, arguing that shipment round the Cape of Africa was commercially and
fundamentally different. The court held that the contract was not frustrated. T
were, therefore, liable for breach - the change in circumstances was not
fundamental. Maritime National Fish v Ocean Trawlers [1935] AC 524 Maritime chartered from Ocean a vessel which could only operate with an otter
trawl. Both parties realised that it was an offence to use such a trawl without
a government licence. Maritime was granted three such licences, but chose to use
them in respect of three other vessels, with the result that Ocean's vessels
could not be used. It was held that the charterparty had not been frustrated.
Consequently Maritime was liable to pay the charter fee. Maritime freely elected
not to licence Ocean's vessel, consequently their inability to use it was a
direct result of their own deliberate act. Walton Harvey Ltd v Walker & Homfrays Ltd [1931] 1 Ch 274 The defendant's granted the plaintiffs the right to display an advertising
sign on the defendant's hotel for seven years. Within this period the hotel was
compulsorily acquired, and demolished, by a local authority acting under
statutory powers. The defendants were held liable in damages. The contract was
not frustrated because the defendant's knew, and the plaintiffs did not, of the
risk of compulsory acquisition. They could have provided against that risk, but
they did not. EFFECTS OF FRUSTRATION Gamerco v ICM/Fair Warning (Agency) Ltd [1995] 1 WLR 1226 The plaintiffs, pop concert promoters, agreed to promote a concert to be held by the defendant group at a stadium in Spain. However, the stadium was found by engineers to be unsafe and the authorities banned its use and revoked the plaintiffs' permit to hold the concert. No alternative site was at that time available and the concert was cancelled. Both parties had incurred expenses in preparation for the concert; in particular the plaintiffs had paid the defendants $412,500 on account. The plaintiffs sought to recover the advance payment under s1(2) Law reform (Frustrated Contracts) Act 1943, and the defendants counterclaimed for breach of contract by the plaintiffs in failing to secure the permit for the concert. It was an implied term of the contract that the plaintiffs would use all
reasonable endeavours to obtain a permit, yet once the permit was granted they
could not be required to guarantee that it would not be withdrawn. The contract
was frustrated essentially because the stadium was found to be unsafe, a
circumstance beyond the control of the plaintiffs. The revocation of the permit,
subsequent to its being obtained by the plaintiffs, was not the frustrating
event; the ban on the use of the stadium was. Under s1 of the 1943 Act, the
plaintiffs were entitled to recover advance payments made to the defendants. The
court did have a discretion to allow the defendants to offset their losses
against this, but in all the circumstances of the present case the court felt
that no deduction should be made in favour of the defendants and their
counterclaim should be dismissed. BP Exploration v Hunt [1982] 1 All ER 925 See law report at p939C-p940C.
|
|
|
| Home | About | Search | Links | Message Boards | Revision Guides | Photos | Contact |